Kennedy Newton Water Main - North Section

​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​

 

 

Kennedy Newton Water Main - North SectionKennedy Newton Water Main - North Section<div class="ExternalClass87362E197FFD41FC93E15A1CD7324803"><p></p><p>Metro Vancouver is constructing the Kennedy Newton Water Main in Surrey and Delta to meet the growing demand for drinking water in the region. The new water main will ensure continued delivery of high-quality drinking water to residents and businesses south of the Fraser River.</p><p>This new water main is over eight kilometres long and is 1.8 metres in diameter. Construction has been divided into five sections due to its large size and length.</p><p>The North Section of the water main, located in Surrey, is approximately one kilometre long and runs from Kennedy Park Reservoir at 90 Avenue, down Holt Road and ends at Scott Road and 88 Avenue. This is the final section to be constructed. </p><p>Construction of the North Section is expected to begin in 2024 and will be completed in 2026. Once this section is complete, Metro Vancouver will return to connect the new water main to the existing drinking water system.<br></p></div>City of SurreyProject

 

 

Construction UpdateConstruction Update<div class="ExternalClass7E25C93ED7F34FEA82EEAF6D6BAD69DF"><p>​Crews are completing the final work on the section with the focus on the valve chamber at 90 Avenue and Holt Road, as well as the excavation of valve chambers at Kennedy Park. <br></p><p>In 2026, crews will be back to connect the new water main into the existing water distribution system. We will keep the community informed before this work occurs and provide more information as it becomes available.<br></p><p>Learn more in our <a href="/services/water/ConstructionDocuments/2025-december-kennedy-newton-water-main-north-and-south-sections-update.pdf">December newsletter.​</a><br></p></div>3/2/2026 8:00:00 AM

 

 

Kennedy Newton Water Main - North Sectionhttps://metrovancouver.org/services/water/ConstructionImages/_t/kennedy-newton-water-main-north-section-map_jpg.jpgKennedy Newton Water Main - North Section
Kennedy Newton Water Mainhttps://metrovancouver.org/services/water/ConstructionImages/_t/kennedy-newton-water-main-north-section-all-map_jpg.jpgKennedy Newton Water Main
Graphic - Timeline - Kennedy Newton Water Main - North Sectionhttps://metrovancouver.org/services/water/ConstructionImages/_t/Graphic-Timeline-Kennedy-Newton-Water-Main-North-Section_jpg.jpgGraphic - Timeline - Kennedy Newton Water Main - North Section

 

 

Project activitiesProject activities<div class="ExternalClass98EF71889F134AC7B3657F2C147735AE"><div><ul><li> <strong>Prepare the s​ite</strong>: Ahead of major construction activities, crews will install tree protection fencing, set up a site trailer, deliver equipment, install temporary fencing and signage, and identify utilities within the project area.</li><li> <strong>Relocate existing utilities</strong>: Construction crews will relocate underground utilities to accommodate the new infrastructure.</li><li> <strong>Install the water main</strong>: The new water main will be installed in segments. This work will involve excavating a large trench, placing wall supports to secure the excavated area, installing a steel pipe, and restoring the impacted roadway with temporary asphalt before moving to the next segment. </li><li> <strong>Construct a tunnel and two tunnel shafts</strong>: Construction crews will build two eight-metre-deep shafts on 88 Avenue on either side of the Southern Railway. Then, a microtunnel boring machine will dig a 50-metre-long tunnel under the railway. Once tunnelling is complete, crews will install the new water main inside the tunnel. </li><li> <strong>Construct three underground valve chambers</strong>: A large chamber will be constructed at the intersection of 90 Avenue and Holt Road. Two smaller chambers will be constructed on the south side of Kennedy Park. This work will include excavating a large pit for each valve chamber, installing wall supports, building a concrete structure, and installing piping and other equipment.</li><li> <strong>Clean and test the new water main</strong>: The new water main will be pressure tested, disinfected, and flushed. </li><li> <strong>Restore the project area</strong>: All impacted areas including roadways, curbs, and landscaping will be permanently restored to previous or better conditions.</li><li> <strong>Connect the new water main</strong>: The new water main will be connected to the existing water distribution system.​<br></li></ul></div></div>
Work hoursWork hours<div class="ExternalClass40EEC5EFD974454AAF7D80D07A42B582"><p>Typical work hours will be:</p><ul><li><strong>Monday to Saturday: </strong>7:00 am and 10:00 pm</li><li><strong>Sundays</strong>: No work planned</li></ul><p>All work will comply with the City of Surrey bylaws or granted bylaw variances. There may be times when construction crews will need to work longer hours to complete critical activities safely and efficiently. Metro Vancouver will notify the community about these activities in advance.​<br></p></div>
Impacts and mitigationImpacts and mitigation<div class="ExternalClass5655EA29A3CB490B92F0966C0F9ABDC4"><p></p><div>Metro Vancouver recognizes the construction of Kennedy Newton Water Main – North Section will impact local residents and businesses. During construction, the community will experience noise and vibration, parking restrictions, and partial or full road closures along 90 Avenue, Holt Road, and 88 Avenue. <br></div><div><br></div><div>Wherever possible, construction crews will implement measures that will prevent or reduce construction impacts, including:<br></div><div><br></div><div><strong>Reduce noise and vibration</strong></div><div><ul><li>Avoid scheduling work that requires noisy or high-vibration equipment before 8:00 am </li><li>Minimize nuisance noise such as idling or warming up heavy equipment </li><li>Monitor noise and vibration periodically to ensure the work is compliant with the City of Surrey bylaws and granted bylaw variances</li></ul></div><div><strong>Keep people moving safely and efficiently</strong></div><div><ul><li>Place traffic control personnel, detour signage, and other traffic management resources to help people moving near work areas</li><li>Maintain access to homes as much as possible; however, residents may experience delays in accessing driveways when active construction is taking place outside of their home </li><li>Maintain at least one access point to businesses at all times</li><li>Ensure emergency service vehicles always have access to residences and businesses</li><li>Ensure sidewalks and pedestrian paths remain accessible or have detour options</li><li>Maintain access to the northern row of parking spots in Kennedy Park</li></ul></div><div><strong>Manage cleanliness, air quality, and dust</strong></div><div><ul><li>Water or sweep the streets to keep the site and surrounding areas clean</li><li>Cover construction vehicles, such as dump trucks, when travelling to and from the site, to reduce dust​<br></li></ul></div></div>
EngagementEngagement<div class="ExternalClass5941249F783E4D61B9084826372B07E7"><p>​​At Metro Vancouver, we make decisions that impact the 2.8 million residents that live in our region. Metro Vancouver engages municipalities, businesses and the general public whenever we are working on a new program, policy, or project across our service areas. Learn more about our <a href="/about-us/community-engagement" target="_blank">engagement princip​les​</a>.<br></p><div> <strong>Working with the community</strong></div><div>Metro Vancouver is committed to minimizing construction impacts and keeping the community informed as the project progresses. We will:</div><div><ul><li>Have a dedicated community liaison to address any questions or concerns from the community</li><li>Notify residents and businesses along the project area about upcoming construction activities via print notifications, email, project webpage, and on-site signage</li><li>Work closely with the City of Surrey, residents, and businesses to identify and mitigate construction impacts​<br></li></ul></div></div>
Project materialsProject materials<div class="ExternalClassEC993E3050184897A927931F4C77C388"><p> <strong>Fact sheets</strong></p><ul class="fa-ul"><li>​​ <span class="fa-li"> <i class="fa-light fa-file"></i></span>​<a href="/services/water/ConstructionDocuments/kennedy-newton-water-main-north-section-fact-sheet.pdf">Fact Sheet - Kennedy Newton Water Main - North Section​ ​</a><br></li></ul><p> <strong>Newsletters</strong>​<br></p><ul class="fa-ul"><li><a href="/services/water/ConstructionDocuments/2025-december-kennedy-newton-water-main-north-and-south-sections-update.pdf">2025 - December 17 - Project Update and Holiday Schedule</a><br></li><li>​​ <span class="fa-li"> <i class="fa-light fa-file"></i></span>​<a href="/services/water/ConstructionDocuments/kennedy-newton-water-main-north-section-newsletter-april-2025.pdf">2025 – April 25 – Water Main and Valve Chambers Construction Update​​ ​</a><br></li><li>​​ <span class="fa-li"> <i class="fa-light fa-file"></i></span>​<a href="/services/water/ConstructionDocuments/kennedy-newton-water-main-north-section-newsletter-november-2024.pdf">2024 – November 14 – Water Main Construction Starts on Holt Road​ ​</a><br></li><li>​​ <span class="fa-li"> <i class="fa-light fa-file"></i></span>​<a href="/services/water/ConstructionDocuments/kennedy-newton-water-main-north-section-newsletter-june-2024.pdf">2024 – June 7 – Upcoming Construction ​</a><br></li></ul></div>
Related linksRelated links<div class="ExternalClassECEC4AA435C9406B8C8DFD263B1CDDB4"><ul class="fa-ul"><li> <span class="fa-li"><i class="fa-light fa-link"></i></span> <a href="/services/water/the-regional-system" target="_blank" title="Regional Drinking Water System">Regional Drinking Water System</a><br></li><li> <span class="fa-li"><i class="fa-light fa-link"></i></span> <a href="https://www.itsalldrinkingwater.ca/">Water conservation tips</a>​​<br></li></ul></div>​<br>

 

 

Summer 2024 - Fall 2024Summer 2024 - Fall 2024<div class="ExternalClassFA6183909DCA40168A1EC5F9E9B2B550"><p>Site Preparation​<br></p></div>0
Summer 2024 - Summer 2026Summer 2024 - Summer 2026<div class="ExternalClassCD158A165BC848EEA1B9027ACE0E4A42"><p>​​Construction​<br></p></div>1
Summer 2026 - Fall 2026Summer 2026 - Fall 2026<div class="ExternalClassC564C05C20F748709E3008F4F5A9600E"><p>​Restoration<br></p></div>0
2026 - 20272026 - 2027<div class="ExternalClass244B42DD0CA2486297BA050966656D0C"><p>​Water Main Connection<br></p></div>0

Contact us​​


Community liaison
Monday – Friday
8:00 am – 4:30 pm

  • Email
  • 604-432-6200​​​

After hours emergencies

  • 604-451-6610​​​​

Stay connected


Subscribe to our mailing list to receive updates about our water projects.

Sign Up​​​​​​​​

This website uses cookies to ensure you get the best experience. By continuing to use this site, you accept our use of cookies. View our privacy statement.